Executing and Closing Project

Ace your studies with our custom writing services! We've got your back for top grades and timely submissions, so you can say goodbye to the stress. Trust us to get you there!


Order a Similar Paper Order a Different Paper

PPMP 20010:
Executing and Closing Project
Assessment 1 – Part A & B
Project Status & Exception Report
30 Marks
Assessment 1 – Outline
• Individual Assignment
• Due Date: Monday, Week 7
• Case Study for Assessment 1 & 2
• Assessment 1 (Part A & B) template
• To be completed using the given template ONLY
• Submission format:
– MS Word, checked by Turnitin software
2
Assessment 1 Alignment to the
Unit Learning Outcome
• Learning Outcome 3 (from Unit Profile)
– Define and justify project event-driven and time-driven
controls for a case study project.
3
Academic Learning Centre (ALC)
• Attend information and training sessions
arranged by ALC
• You must be aware of:
–CQU’s latest Academic Integrity Policy
–Plagiarism and contract cheating
–Referencing
–Group work skills
–Written communication skills
4
Case Study (Project)
• Case study is Sydney CBD South East Light Rail project.
• Download the case study from the Assessment section in
Moodle.
• You need to complete Assessment 1 & 2 in the context of
this case study.
• A number of URLs containing the information are given in
the case study document.
• This information is not comprehensive.
• You need to widen your research until an in-depth
understanding of this project is reached.
5
Case Study (Project)
• As project manager, you need to compile the following
reports in the context of given case study (project).
– Project Status (Progress) Report,
– Project Exception Report,
– Project Audit & Closure Report,
– Project Governance Report
– For assignment purpose, you may need to make certain
assumptions as well.
6
Assessment 1 Part A – Project Status Report
• Project status report is a tool used throughout the life of a
project to provide information on how the project is
proceeding and progressing.
• This report is a vital communication tool aimed at the
sponsor, project board and/or steering committee.
• Download the Assessment 1 Template from the
Assessment section in Moodle.
7
Project Status Report
• Project status report usually contains the following
sections:
– Gantt Chart
– Performance (Variance) Analysis
– Estimated Cost At Completion (EAC)
– Forecast Completion Date
– To-Complete Performance Index (TCPI)
– S-Curve
– Milestone Report
– Exception Report
8
Gantt Chart
• Gantt Chart invented by Henry Gantt in 1915.
• It illustrates the project schedule.
• It illustrates the start and finish dates of the
project tasks/activities.
• It also shows precedence (sequence) of tasks.
• Tasks constitute the Work Breakdown Structure
(WBS) of the project.
• etc.
9
Gantt Chart – Example
10
Performance (Variance) Analysis
• Performance analysis is used to check the progress / status
of the project during Execution phase.
• Status of every task, sub-task, summary task and the
project is measured at regular intervals of time.
• CPI% = (EV/AC) * 100
– CPI% < 100% – actual cost is above the planned cost
– CPI% = 100% – actual cost is the same as planned cost
– CPI% > 100% – actual cost is below the planned cost
• SPI% = (EV/PV) * 100
– SPI% < 100% – less work completed than planned
– SPI% = 100% – work completed as planned schedule
– SPI% > 100% – more work completed than planned
11
Estimated cost At Completion (EAC)
• EAC is the forecasted cost of the project at completion, as the
project progresses …
• BAC – Budget At Completion (Total planned budget of the
project) = Total PV
• Use appropriate method based on the assumption.
• Method 1: based on actual cost to date, and predicts future work
will be accomplished at the budgeted rate
– EAC = AC + (BAC – EV)
• Method 2: assumes what the project has experienced to date is
expected to continue
– EAC = BAC / CPI
• Method 3: based on both CPI and SPI factors, when project
schedule is impacting the estimate cost to complete the project
– EAC = AC + [ (BAC – EV) / (CPI x SPI) ]
To-Completion Performance Index (TCPI)
• TCPI is a measure of cost performance that is required
to be achieved with the remaining resources in order to
meet specified management goals.
• TCPI is expressed as a ratio of the cost to finish
outstanding work to the remaining budget.
• TCPI = Work Remaining / Funds Remaining
• Assumption is that BAC is still valid:
TCPI = (BAC-EV) / (BAC-AC)
• Assumption is that BAC is not valid anymore:
TCPI = (BAC-EV) / (EAC-AC)
Forecast Completion Date
• Forecast completion date forecasts the end date of the
project, as the project progresses …
• It is derived from the Schedule Performance Index (SPI)
• Forecast Completion Date = Total duration of the project / SPI
• If SPI < 1, then project is expected to be completed after
the scheduled completion date.
• If SPI = 1, then project is expected to be completed as
per the scheduled completion date.
• If SPI > 1, then project is expected to be completed
before the scheduled completion date
S-Curve
• S-Curve tracks the project progress over time.
• It gives a quick overview about status of the project.
• It shows PV, EV & AC for the project.
Milestone Report
• Milestone is an event on a schedule, which marks
the completion of a key activity.
• Progress on the milestones is provided in this
section.
• Any issues with the milestones are also listed here.
Assessment 1 Part A – Project Status Report
• Assessment 1 Part A is about the project status
(progress) at a given point of time during the
Execution phase.
• Main tasks (activities) of the case study are provided
in the template.
• Gantt chart is provided in the template.
• PV, EV & AC data is also be provided in the template.
• You are required to analyse the project progress in
the context of the given case study and data
provided.
Assessment 1 Part B – Project Exception Report
• An exception report is a tool used when the project or
stage is forecast to exceed given tolerances
• This report is a vital communication tool aimed at the
sponsor, board members and/or steering committee,
making suggestions and asking for guidance from higher
authority.
18
Assessment 1 Part B – Project Exception Report
• Establish the need for an exception report
– Provide your motivation to compile and raise a costoverrun or behind-schedule exception report to the
project board along with appropriate reasons for your
decision
– Maximum 500 words
19
Assessment 1 Part B Contd.
• Exception title
– An overview of the cost-overrun or behind-schedule
exception being reported
• Cause of the exception
– A description of the cause of a deviation from the current
plan
• Consequences of the deviation
– What the implications are if the deviation is not addressed
for the project, Corporate, programme management or the
customer
Assessment 1 Part B Contd.
• Options
– What 2-3 options are available to address the deviation
and the effect of each option on the business case, risks,
and tolerances.
• Recommendation
– Of the available options, which is recommended, and why?
• Lessons
– What can be learnt from the exception, on this project or
for future projects?

Writerbay.net

Looking for top-notch essay writing services? We've got you covered! Connect with our writing experts today. Placing your order is easy, taking less than 5 minutes. Click below to get started.


Order a Similar Paper Order a Different Paper