The Tuff Wheels was getting ready to start its development project for a new product to be added to its small motorized vehicle line for children. The new product is called the Kiddy Dozer. It will lo

Ace your studies with our custom writing services! We've got your back for top grades and timely submissions, so you can say goodbye to the stress. Trust us to get you there!


Order a Similar Paper Order a Different Paper

The Tuff Wheels was getting ready to start its development project for a new product to be added to its small motorized vehicle line for children. The new product is called the Kiddy Dozer. It will look like a miniature bulldozer, complete with caterpillar tracks and a blade. Tuff Wheels has forecasted the demand and the cost to develop and produce the new Kiddy Dozer. The following table contains the relevant information for this project.

Development cost               $750,000

Estimated development time          9months

Pilot testing                            $200,000

Ramp-up cost                         $400,000

Marketing and support cost     $150,000 per year

Sales and production volume        60,000 per year

Unit production cost                      $100

Unit price                                         $155

Interest rate                                     8%

Tuff Wheels also has provided the project plan shown as follows. As can be seen in the project plan, the company thinks that the product life will be three years until a new product must be created.

Assume all cash flows occur at the end of each period.

a. What is the net present value (discounted at 8%) of this project? Consider all costs and expected revenues. (Enter your answer in thousands of dollars. Perform all calculations using Excel. Do not round any intermediate calculations. Round your answer to the nearest thousand.)

b. What is the impact on NPV for the Kiddy Dozer if the actual sales are 50,000 per year? 70,000 per year? (Enter your answer in thousands of dollars. Perform all calculations using Excel.  Do not round any intermediate calculations. Round your answer to the nearest thousand.)

c. Based on the original sales level of 60,000, what is the effect on NPV caused by changing the discount rate to 9%, 10%, or 11%? (Enter your answer in thousands of dollars. Perform all calculations using Excel. Do not round any intermediate calculations. Round your answer to the nearest thousand.)